From March 11th of this year ..
"Mr Harris said Karara was on track to run at 75 per cent of its 8 million tonne-a-year production capacity by the end of the month. It would still likely need between $150 million and $200 million in new capital to re-engineer its processing plant to help it reach nameplate production."
http://au.news.yahoo.com/a/21914661/