At last FERC has issued its Engineering Information Request and provided LNG with the usual 20 days to respond. It contains 103 queries, many of which looks pretty straightforward, but at least the team can respond.
I believe this is the penultimate IR and await confirmation from the company that this is so. Hopefully the other will follow quickly.
Issuance 20141209-3004 12/09/2014 12/09/2014 CP14-347-000 Letter requesting K & L Gates, LLP to provide additional information w/in 20 days re engineering data for the Magnolia LNG Project under CP14-347. Availability: Public FERC Correspondence With Applicant / Request for Additional Information PDF 89K FERC Generated PDF 188K INFO FILE