ALB albion resources limited

positive bfs for nickel deposit

  1. 2,547 Posts.
    The indicative schedule for Project Implementation at Enterprise is as follows:
    • Commence surface earthworks Q4 2006
    • Engineering, design and procurement Q3 2006 to Q2 2007
    • Supply – equipment and fabrication Q1 2007 to Q1 2008
    • Installation:
    o Process plant Q1 2007 to Q2 2008
    o Infrastructure Q4 2006 to Q1 2008
    o Commissioning Q2 2008.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
6.7¢
Change
-0.002(2.90%)
Mkt cap ! $8.839M
Open High Low Value Volume
6.9¢ 6.9¢ 6.7¢ $28.88K 424.8K

Buyers (Bids)

No. Vol. Price($)
1 52000 6.6¢
 

Sellers (Offers)

Price($) Vol. No.
6.9¢ 45000 1
View Market Depth
Last trade - 11.23am 21/07/2025 (20 minute delay) ?
ALB (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.