    July/August 2017, bring on the announcement.

    3.3. Timeframe and Schedule The Project is planned to commence in July / August 2017. A summary of the proposed schedule is provided as below.
    Table 3: Project schedule Activities Approximate duration Indicative timing Environmental considerations Civil works 15 - 20 days
    Q3 2017 12 hour operation Clearing of native vegetation Mobilisation of crew and equipment 10 - 15 days
    Q3 2017 Movement of vehicles and fauna impact potential Drilling, logging and P&A 20 – 30 days
    Q3 / Q4 2017 24 hour operations – fauna impact potential from driving at dawn / dusk General impact of site operations The timeframe and schedules for subsequent phases of the Project (decommissioning, care and maintenance and rehabilitation) will be determined as required at a later stage.
 