"Of interest NEWM204 appears to have intersected steep dipping uranium mineralization which was not previously recognized at this project. Sampling on the El Hussein project area identified the following zones from surface sampling: • 1 metre @ 0.55% U3O8 • 7 metres @ 0.45% U3O8 • 1 metre @ 0.14% U3O8 This sampling is over a strike length of 400 metres and occurs within a steep dipping structure. Previous drilling has been vertical and failed to test this zone. The target is for both steep and stratabound mineralization at depth. Laramide plans to test this zone during the 2007 field season. Work will continue on these projects in 2007 field season. Drilling is expected to start in June 2007 to continue on The North East Westmoreland Project. This will be followed up by testing of the El Hussein target and further grass roots work."
Laramide 2006 Annual Report
NUP Price at posting:
0.0¢ Sentiment: Buy Disclosure: Held