email recieved from CEO this morning for those interested.
Monday, 13 October 2003
Dear Phil,
In relation to your e-mail below, we are currently working through the commissioning at Warrego. Some plant components and support infrastructure have achieved practical completion and have been released to Giants Reef. This includes the crushing circuit, bore field, tailings dam, power station, office facility etc. The ball mill is scheduled to achieve practical completion today. To-date commissioning has proceeded without any major impediment. I expect our first gold pour will be in the next week or so depending on how long the carbon takes to load with gold.
Thank you for your interest in our company.
Regards,
J Ariti
Chief Executive Officer
Giants Reef Mining Limited