    Back on topic, more or less.. I think a lot of people have overlooked the fact that the initial announcement concerning the assays received from the June drilling indicated that results from only 11 of the initial 29 drilling holes had been received with the remaining results due in the following 4 weeks.. So the next lot of 'U' results due are from the initial drilling conducted not from the August drilling and these should be arriving shortly.

    As below from announcement on 24/7

    Program Details
    The drilling program conducted in June totaled 1,648 metres of RC drilling comprising 29
    holes. The maximum hole depth was 98 metres with an average hole depth of 56 metres.
    Ground conditions limited drilling production rates. This prompted the sensible decision
    during the program to modify the average planned hole depth from 100 to 50 metres, allowing
    a greater number of holes to be drilled and area covered in the planned time frame.
    Twenty one drill holes were completed on the Henri anomaly where previous trenching work
    yielded strong surface mineralisation. Two drill sections approximately 200 metres apart were
    completed in addition to some isolated holes off section.
    At Para, located approximately 800
    metres south of Henri, two sections of
    drilling with holes spaced at 100 metres
    were completed. Each section comprised
    three drill holes.
    Two drill holes were completed on the
    Tahbilk anomaly approximately 700
    metres north of Henri.
    All holes were geologically logged on site
    by Western Metals staff. Sampling was
    conducted on one metre intervals using
    representative sampling techniques.
    Delays in the arrival of downhole
    geophysical equipment has postponed
    the collection of downhole geophysical
    data until August. All completed holes
    have been cased to allow the geophysical
    surveys to be conducted.
    Samples were submitted to the ALS
    Chemex laboratory in Tanzania for
    preparation and then dispatched to their
    Australian laboratory for analysis.
    To date results from 11 of the Henri drill holes have been received by Western Metals, with
    results of the remaining 18 holes expected in the coming four weeks.
 