-Finance ageeement: 6 months at best.
-Engagement of Project delivery team: 2 months after finance at best.
-Engagement of design and construction team: Depends on if NFC get on board. If they do it’ll probably be in parralel with finance or within 1-2 months. Otherwise what happens? Single select contractor, competitive tender? If so add 3 months post finance to engage someone suitable. We’re at 9 months now.
- Finalise design, engineering and relevant approvals: 6 months at best. We’re at 18 months now AKA approx Aug. 2019.
- In parrell to finalising the design I imagine a site team and equipment will be getting procured and sent to citronen; how is heavy plant and construction equipment sent there and from where?
- Prefabricate relevant equipment: 3 months at best.
- Ship equipment (to where? Where can this be received? Is a port nearby?) allow 6-8 weeks from completion of prefabricated items. We’re in February 2020 now. Probably more like march- April 2020 given that this shipping will be over Christmas and the Chinese New Year.
Now we have 20 months to build the plant and associated infrastructure - power, roads, port? What about the port? What needs to be built to get the zinc on the ships?? Then everything needs to be successfully commissioned... I guess there definitely won’t be any delays or issues with a project like this... yeah 2022 isn’t reasonable, sorry Yatchy. You’ll be mining before Christmas this year.
- Forums
- ASX - By Stock
- IBG
- Ann: Quarterly Activities Report
Ann: Quarterly Activities Report, page-63
Featured News
Add IBG (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.3¢ |
Change
0.000(0.00%) |
Mkt cap ! $5.500M |
Open | High | Low | Value | Volume |
0.2¢ | 0.3¢ | 0.2¢ | $22.93K | 7.656M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
56 | 99871037 | 0.2¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.3¢ | 1150366 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
56 | 99871037 | 0.002 |
23 | 118450982 | 0.001 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.003 | 1150366 | 1 |
0.004 | 30303675 | 14 |
0.005 | 7450823 | 7 |
0.006 | 3966350 | 9 |
0.007 | 1940300 | 4 |
Last trade - 15.51pm 11/11/2024 (20 minute delay) ? |
Featured News
IBG (ASX) Chart |
The Watchlist
I88
INFINI RESOURCES LIMITED
Charles Armstrong, MD & CEO
Charles Armstrong
MD & CEO
Previous Video
Next Video
SPONSORED BY The Market Online