Hopefully no news means not too expensive reasons for delay??
Press from May 8:
“Gascoyne says that the process plant is “effectively complete” with components being commissioned with ore and progressively tested up to their design capacities, adding that “first gold production expected in around 10 days”. If the commissioning programme is successful, it schedules Gascoyne’s first gold production for 18th May 2018.”
https://*********.com.au/gascoyne-resources-golden-endowment-western-australia/
As to what might cause delays, here’s an old press release from Oceana Gold detailing various problems that arose during that mine’s commissioning process in 2006:
https://www.oceanagold.com/wp-content/uploads/2017/06/170626-Haile-Commissioning-Status.pdf
- Forums
- ASX - By Stock
- SPR
- Ann: Ore Commissioning Underway Ahead of Schedule & Under Budget
Ann: Ore Commissioning Underway Ahead of Schedule & Under Budget, page-50
-
- There are more pages in this discussion • 8 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add SPR (ASX) to my watchlist
(20min delay)
|
|||||
Last
$1.29 |
Change
0.035(2.80%) |
Mkt cap ! $1.429B |
Open | High | Low | Value | Volume |
$1.26 | $1.31 | $1.25 | $8.109M | 6.342M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 29952 | $1.29 |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
$1.29 | 40389 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 29952 | 1.285 |
1 | 8000 | 1.270 |
1 | 23000 | 1.265 |
9 | 136533 | 1.250 |
3 | 33500 | 1.245 |
Price($) | Vol. | No. |
---|---|---|
1.290 | 40000 | 1 |
1.295 | 17477 | 2 |
1.300 | 2223 | 1 |
1.305 | 26020 | 3 |
1.310 | 49603 | 2 |
Last trade - 16.10pm 11/10/2024 (20 minute delay) ? |
Featured News
SPR (ASX) Chart |