    stuff barrow island - where is the news flow re ps3 - the last update was two weeks ago....

    At 31/5 they were at 4619m with the forward plan being:

    "Run the 11-3/4” liner before drilling the 10-5/8” hole from 4,619 metres MD to approximately 5,160 metres MD. Following this, a 9-5/8” casing will be set before the 8-1/2” hole section is drilled to the top of the primary Caley Member section, which is expected to be intersected at a depth of approximately 5,360 metres MD"

    I thought the comms plan was to report on milestones so either the drill bit is stuck or wtf??? No asx announcement re casing being set at 5360m after 2 weeks from a depth of 4619m is making me a little nervous - if all is going to plan why not report good news re 5630m casing.....