ASX announcement Month and Year
|
YANDAL WEST (gold) May Queen site
|
YERRIDA SOUTH Chisel (copper)
|
1 |
OCTOBER 19------------------ 21------------------- 24------------------ 31-------------------
|
19 Drill Program announced PHASE I [ 0 days] 21 RC drill mobilized to site [2 days ] 24 Drilling commences at Yandal. To take 3 weeks, 2 weeks turnaround. [0 days ] 31 Yandal drilling program begun [7 days ]
|
19 ------NIL 21 ------NIL 24 ------NIL 31 --Chisel Gravity Survey Program begins (Newexco )
|
2 |
NOVEMBER 9----------------- 15---------------- 28---------------- 30---------------
|
9 Yandal PHASE I 22 holes drilled 2297m [ 16 days] Assays in 2-3 weeks. Drilling to restart in early December 28 Yandal ASSAY RESULTS [ in 2 weeks 5 days]. PHASE 2Starts next week. 30 NOV 28 results RE-RELEASED RC DRILL RIG USE 2297M PHASE I OCT 21/ Nov 28 38 days TO COMPLETE
|
9 ---------NIL 15 Chisel Gravity Survey completed [ 16 days ] 28 ---------NIL 30 ---------NIL
|
3 |
DECEMBER 4-------------------- 8--------------------- 16------------------- 22------------------
|
4 $2M of funds raised for Yandal Gold 8 Yandal West PHASE II 3000m planned [ 0 days] 16 GTE General Meeting 22 Yandal West PHASE II 1852m RC drilling done [ 14 days ] Assay results in Mid January. More drilling late January RC DRILL RIG USE 4149M
|
4 ---------NIL 8 ---------NIL 16 GTE General Meeting 22 ---------NIL
|
4 |
JANUARY 30----------------- 31-----------------
|
30 Yandal ASSAY RESULTS [ 15 days later than planned ] 31 Q4 2017 Activities Report Q4 2017 Financial Report 2097m of drilling done. A further 1200m of drilling planned AS WEATHER PERMITS [ NO drilling late January] RC DRILL RIG USE 4394M
|
30 ---------NIL 31 Q4 2017 Activities Report Q4 2017 Financial Report Chisel drill planning has begun
|
5 |
FEBRUARY 14-----------------
|
14 No drilling at Yandal West due to WET weather RC DRILL RIG USE 4394M
|
---------NIL
|
6 |
MARCH 13-------------------- 15-----------------
|
13 Yandal West PHASE II 1200m left in 3000m program. Now planning a further 1500m, then Diamond drilling after OTV survey ACTUAL MAR DRILLING 1647m (ASX May 14) 15 Half Yearly Report RC DRILL RIG USE 6041M
|
13 ---------NIL 15 ---------NIL Half Yearly Report
|
7 |
APRIL 4--------------------- 18-------------------- 27------------------- 30-------------------
|
4 ---------NIL Awaiting Assays 18 ---------NIL Awaiting Assays 27 ---------NIL Awaiting Assays 30 ---------NIL Awaiting Assays Q1 2018 Activities Report Q1 2018 Financial Report
|
4- Chisel drill target identified. 1200m RC drilling planned, in conjunction with Newexco. 18 -Chisel drilling commenced. 1000m (5x 200m deep holes) 27 - 3 holes drilled (600m) RC DRILL breaks down . MAJOR OVERHAUL REQUIRED. Back in action in June. 30 -Q1 2018 Activities Report Q1 2018 Financial Report RC DRILL RIG USE 6641M BREAKS DOWN [ COULD IT HAVE BEEN CHECKED & OVERHAULED IN FEB ? ] [Possible outback field crew vs Perth planning crew issue here ? ]
|
8 |
MAY 3------------------- 10----------------- 14------------------
|
3 ---------NIL Awaiting Assays SANDFIRE to aerially examine Yerrida North 10 Investor Presentation 14 Yandal West PHASE II 1647m DONE. A futher 1500m planned [ PHASE II Part 3 ? ] RC DRILL RIG USE 0M [ NIL being repaired ]
|
3 ---------NIL 10 Investor Presentation 14 ---------NIL
|
9 |
JUNE 19----------------
|
19 Yandal West 2,316m RC drilled - 26 holes. SO MORE THAN the initial 1500m ABOVE. ASSAYS IN 6 weeks. [ NOTES {1} March ASSAYS weren’t released until mid –May , thus between 6 (mid March at best to 8 weeks at worse scenario). {2} It could take so long, due to QUEUING of various WA mining co’s wanting results, and GTE being so small a co ! RC DRILL RIG USE 2316m
|
19 ---------NIL NOTE ASX APR 30 company mentioned the choice of EITHER Chisel or Yandal, once the RC drill was back in operation NOTE: could GTE drag back the RC drill back to Chisel in the intervening 6 weeks wait ? NOT MENTIONED in June 19th announcement. A shareholder could call the co. ????
|
10 |
|
THE END
|
|