G'Day tgallagh-No jumping to conclusions needed .
Hm-3 is not continuously supplied-there is no conveyor feeding HM-3.
Mh-3-is a manual operation -hose & poker , its still very worthwhile as its very high grade, high grind, high recovery.
HM-3 is also very simple to shut down-no big wind down required.
Unless its an jammed & in operatable the hammer change out would occur when production is finished for the day
otherwise you loose production time as plant sits idle for 12 hrs you do it then.
Not assumption -that's what you do in production -never shut down unnecessarily-full stop.
A hopper & automated feed system Shute can be adapted directly overhead that would allow for an adjustable
continuous feed rate .
ATM-revenue generation is the priority-system is operating -check-tick.
Improvements can be made according to scale required, this is unlikely to be known with bulk samples pending
a different production through-put may be required-lots of variables -hence modify the plant when you have
all the data to make an informed decision.
imo-gltah
salt
- Forums
- ASX - By Stock
- OGX
- Have a Ganda at the Gravity plant running at full spec?
Have a Ganda at the Gravity plant running at full spec?, page-59
-
- There are more pages in this discussion • 116 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
LU7
Discover the strong preliminary feasibility of the Bécancour Lithium Refinery, showcasing resilience in a low pricing environment and a strategic plan to capitalize on future price recoveries
NEWS
Breakthrough programs slash healthcare events, driving a significant A$1.8M+ annual revenue boost