Operations to retrieve the jars and remaining stuck drill string from the hole were unsuccessful. No further attempts are going to be made to extract the stuck pipe, as there is a very low probability of success. A cement plug has been set across the top of the 7 inch liner from 3,720 metres back to 3,680 metres.
The joint venture has now approved a proposal to sidetrack a further time from above the reservoir by milling a window in the 95/8 inch casing at around 3,680 metres, which the drill string will pass through. A new hole would then be drilled from that point to a depth of approximately 4,300 metres with a KCL fluid.
Following the release of the attached announcement, trading in Amity's shares will commence at open tomorrow morning, 9 January 2004.
Regards
Amity Oil Limited www.amityoil.com.au