Grabbed some more. Might be coming good finally and I like Silver a lot.
" Therefore, following the completion of the stacking process of cell 2, which is anticipated to be in the
coming days, the site will move to irrigation of cell 2, whilst undertaking final commissioning and
testing of the Meryl Crowe Circuit and associated infrastructure. This is anticipated to be undertaken
in the week of the 11th of February 2019. Once this has been undertaken and successfully run for
several days, a decision as to the operational readiness, via the review of all safety and
environmental management system will be confirmed, and the site will seek to move into production
based leaching operations, shortly after.
As previously outlined, the Company will continue to update the market and as such the next
announcement regarding the Granite Belt Project will likely pertain to the successful commissioning
and subsequent achievement of silver production, followed by commercial quantities of concentrate
being sold. Following this mile stone, the Company will then fall into normal quarterly reporting with
the forecast production and achievements of the site due in April 2019, as part of the Companies
quarterly reporting and forecasting obligations.
- Forums
- ASX - By Stock
- MRV
- Ann: Progress Report MRV Metals Pty Ltd
Ann: Progress Report MRV Metals Pty Ltd, page-3
-
- There are more pages in this discussion • 8 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)