Hi Z,
Could you please show me your detailed maths behind your 70week assumption.
Last Ann stated:
”Mining and Transport is currently expected to continue for approximately another 10-12 weeks.”
Based on:
”Processing rates are currently approximately 15 tonnes per hour with this rate to be steadily increased over the coming weeks with 25 tonnes per hour being targeted.”
Thank you
- Forums
- ASX - By Stock
- SVG
- Ann: First Gold Pour from Agate Creek Gold Project
Ann: First Gold Pour from Agate Creek Gold Project, page-54
-
- There are more pages in this discussion • 299 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
NEWS
Antler Copper Project hits major permitting milestone – air quality permit advances to final review
LU7
Discover the strong preliminary feasibility of the Bécancour Lithium Refinery, showcasing resilience in a low pricing environment and a strategic plan to capitalize on future price recoveries
Add SVG (ASX) to my watchlist
(20min delay)
|
|||||
Last
2.2¢ |
Change
0.000(0.00%) |
Mkt cap ! $6.183M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
SVG (ASX) Chart |
Day chart unavailable