    Probably...Perhaps 8-10 days to finish and de-mob.from Simpson, then 7-8 days to rig-up for CBM107001.. Then around about 28 days to drill and complete that well and de-mob...


    Follow that with a further 8(?)days to move to the next location, rig-up and drill CBM 93002, and then perhaps another 28 days drilling.. So we could be looking at a total elapsed time-frame of around two months before the next two PLANNED wells are complete---just in time for Christmas...


    The above timetable is approx. at best and supposes that there is no deviation from current plan and no major mis-haps...either in the field or in the board-room!!
 
watchlist Created with Sketch. Add CTP (ASX) to my watchlist
(20min delay)
Last
5.5¢
Change
0.000(0.00%)
Mkt cap ! $40.70M
Open High Low Value Volume
5.4¢ 5.6¢ 5.4¢ $41.20K 750.9K

Buyers (Bids)

No. Vol. Price($)
1 1270000 5.2¢
 

Sellers (Offers)

Price($) Vol. No.
5.4¢ 540000 1
View Market Depth
Last trade - 15.31pm 26/08/2024 (20 minute delay) ?
CTP (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.