HARDMAN Resources Ltd
Hardman Resources Ltd provides the following progress report on the drilling of the Woodada
#l9 gas well. The well is being drilled within the Woodada Production Licence (PL 5 ) located
approximately 260 kilometres north of Perth, Western Australia. Further details are:
Progress: Current depth of 2,144 metres KB. Drill 8 5 inch (216 m) hole
(Last 24 hours IO 06;OO size from 2,064 metres to 2,144 metres. Pulling out of hole for bit
hours 3/5/02) change.
Geology and
Hydrocarbon Shows: Background gas shows in Basal Kockatea Formation.
Well Location: Located to intersect primary reservoir target approximately
700 metres west of the Woodada #S gas production well.
Primary Target: Gas producing zones within Carynginia Limestone at
approximately 2,200 metres depth.
Secondary Targets: Sandstone within basal Carynginia Formation (between
2,400 metres to 2,500 metres depth), below the Carynginia
Limestone Gas Reservoir.
Sandstones within the Irwin River Coal Measures, between
2,530 metres to 2,800 metres depth.
High Cliff Sandstone (if present) at about 2,820 metres depth.
Web address: www.hdr.com.au Email: [email protected]
03 MAY '82 18:11 FROM TO ASX ANNOUNCEMENT P.82,'84
.Page2...
Note: These secondary objectives below the producing gas
reservoir of the Woodada Gas Field have not previously been
tested.
Drilling of Woodada #l9 commenced on l1 April 2002. A period of 25 days has been estimated
for the completion of drilling and testing operations at Woodada #l9 to an approximate total
depth o f 2,900 metres.
Participants: Hardman Resources Ltd 75%
Bounty Oil & Gas NL 25%
Yours sincerely
HIARDMAN RESOURCES LTD
KATHRYN DAVIES
COMPANY SECRETARY AND
CHIEF FINANCIAL OFFICER
- Forums
- ASX - By Stock
- HDR
- Woodada19 update, 3/5/2002
HDR
hardman resources limited
Woodada19 update, 3/5/2002
-
-
- There are more pages in this discussion • 2 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)