I certainly hope so!
From slide 9 of the Sep preso
Bit late for bullet point #4 ... surely that is already accepted and I read bullet point #3 as an ongoing optimization program.
Which takes us to slide 10 ... with my couple of ticks to show announced completions
@seanbuccs, I'll go with @Pie-O-My estimate but make the observations
(1) I've seen US data (2018) showing combustion turbine plants costing ~US$604 Kw as "construction cost". That put's it at a mere U$3M. But of course no economy of scale or location advantage. Triple it for Australia so US$9M or AUD$12M
(2) Financing
(a) the $18M placement is to
I don't think that rules out requiring additional capital in 2021
(b) the Placement ensures commercial works (stuff in the EPCM gets going) STARTS
Starting and completing can be far apart.
What will confirm the project and thus the funding for completion of stage 1 and stage 2 is FID
Notice it says Stage 1 - FID Planned ... when that says FID Approved then I'll get excited.
- Forums
- ASX - By Stock
- NRZ
- 5MW gas fired power plant
5MW gas fired power plant, page-2
-
-
- There are more pages in this discussion • 2 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add NRZ (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.4¢ |
Change
0.000(0.00%) |
Mkt cap ! $8.724M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
NRZ (ASX) Chart |
Day chart unavailable