    Thanks for bringing this document to our attention regulator.

    There is whole lot in here that underlines how advanced MAK is in planning this mine.

    Section 2.4 Mining Schedule:

    "Mining will commence simultaneously at Arruwurra and Main Zone, with Main Zone Pit C likely to
    be the first of the three Main Zone pits to be developed. Development of Pits A and B is expected
    to commence towards the later part of the first year of operation. Thereafter all pits will be mined
    concurrently to allow blending of ore types to achieve optimum blends for market requirements."

 