CVN 0.00% 15.5¢ carnarvon energy limited

poe operation update available , page-3

  1. 268 Posts.
    Apr 28, 2009 08:30 ET
    Thailand Operations Update

    CALGARY, ALBERTA--(Marketwire - April 28, 2009) - Pan Orient Energy Corp. (TSX VENTURE:POE) -

    THAILAND

    NSE-E2ST1 appraisal well (60-per-cent working interest and operator)

    The NSE-E2ST1 appraisal well is currently producing 32 degree API oil at a stabilized rate of 1,350 barrels per day through casing and tubing choke settings of 26/48" and 14/48" respectively, with no water. The well is on free flow with flowing casing and tubing head pressures of 210 and 170 psig respectively.

    This well is a sidetrack of the earlier drilled NSE-E2 where the main reservoir target was faulted-out but 15 barrels of oil was recovered from a different volcanic zone located in a separate fault compartment from the NSE-E1 structure that is yet to be appraised.

    At least one additional well is planned for the NSE-E1 structure in 2009.

    L44-W exploration well (60-per-cent working interest and operator)

    The L44-W exploration well is currently shut-in while a cement plug is being run to isolate an upper 36 meter thick volcanic from a deeper 16 meter thick volcanic, the two being separated by 63 meters of intervening shale and thin volcanic stringers. Drilling fluid losses indicating good permeability had been encountered in both volcanic zones while drilling.

    During test period #1 the well initially flowed at a maximum of 1,200 barrels of fluid per day (bfpd) with a 30% water cut that climbed to approximately 80% after approximately three hours. At the termination of the test, flowing casing head and tubing head pressures had decreased to 20-30 psig. A subsequent shut-in period saw well head pressures increase to 322 psig.

    During test period #2 the flow rate was restricted to 540 bfpd initially and then further restricted to 250 bfpd with no water (all oil, approximately 32 degree API), the tubing was shut-in and a flowing casing head pressure of 120 psig was observed. After eight hours, the water cut increased immediately to 90% and the test was terminated 9 hours later.

    Initial interpretation of the test data combined with observations from well tests on prior wells suggests that the water is being sourced from the deeper 16 meter thick volcanic zone. This deeper zone is being isolated with a cement plug and testing of the 36 meter thick upper zone is expected to start within the next five days.

    Production testing is being conducted under a 90 day production test allowance from the Thailand Department of Mineral Fuels ("DMF"), as the well is outside any existing production license.

    NSE-H2 appraisal well (60-per-cent working interest and operator)

    The NSE-H2 appraisal well, drilled into the northern down structure portion of the NSE central fault compartment, is currently on production at approximately 420 barrels of oil per day with a 26% water cut as the well continues to clean up, much the same as the nearby NSE-H1 well (currently less than 1% water cut).

    NSE-I1 appraisal/exploration well (60-per-cent working interest and operator)

    The NSE-I1 appraisal/exploration well, located in the NSE north fault compartment is currently drilling ahead at a depth of 64 meters. This is the first well to be drilled in the NSE north fault compartment since the modest L44G-D1 discovery made in 2007 (0.075MM barrels of proved and probable reserves net to Pan Orient assigned in the reserve report as at December 31, 2008 evaluated by Gaffney Cline & Associates Ltd.). The well is located 1.1 kilometers northwest of L44G-D1 and in a separate down thrown fault compartment related to, up dip and larger than that of the NSE-E1 discovery made in 2008.

    The targets include three different volcanic zones between 731 and 1,100 meters (TVD) within a 1.64 square kilometer structural closure entirely outside of the L44G-D1 3P reserve envelope. Success in any one of the 3 targeted volcanic zones has the potential to substantially increase the reserves currently assigned to the NSE north fault compartment.

    Drilling is anticipated to be completed in the next 14 days at which time testing of multiple zones, if justified by drilling results, will be initiated.

    NSE-H3 appraisal well (60-per-cent working interest and operator)

    The NSE-H3 appraisal well is currently drilling ahead at a depth of 570 meters true vertical depth (TVD) towards the top of the main volcanic objective at approximately 850 meters TVD. Drilling is anticipated to be completed in the next 8 days with testing to commence shortly thereafter.
 
watchlist Created with Sketch. Add CVN (ASX) to my watchlist
(20min delay)
Last
15.5¢
Change
0.000(0.00%)
Mkt cap ! $277.3M
Open High Low Value Volume
15.0¢ 15.5¢ 15.0¢ $265.5K 1.746M

Buyers (Bids)

No. Vol. Price($)
2 66750 15.0¢
 

Sellers (Offers)

Price($) Vol. No.
15.5¢ 2227430 6
View Market Depth
Last trade - 16.10pm 07/08/2024 (20 minute delay) ?
CVN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.