Ann: Tombador Mine Construction Complete, page-8

  1. 9 Posts.
    lightbulb Created with Sketch. 3
    As we know, the 1500m infill drilling program commenced on the 26th of October. The investor presentation on the 3rd of December stated that they had drilled over 600m. The quarterly then stated that 1095m had been drilled and the first 14 holes had been sent for testing by the end of Q4.

    I would say that 1095m had been drilled prior to Xmas, as they would have had a week or two off site.

    Basic math suggests they were drilling roughly 130m-140m per week. Infill drilling should be well and truly complete. I expect to see an update this week. If anyone has any further info or has more experience in iron ore drilling/testing I would love to hear your insight.

    Good luck to all holders and let's hope for a significant resource upgrade.
 
watchlist Created with Sketch. Add TI1 (ASX) to my watchlist
(20min delay)
Last
1.4¢
Change
0.000(0.00%)
Mkt cap ! $30.21M
Open High Low Value Volume
0.0¢ 0.0¢ 0.0¢ $0 0
TI1 (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.