Oh no.. The management have just announced up to a 18 month delay on key milestones!!!
In May's presentation
Management announced to have finance completed Q3 2021 - now its 2H 2022 (a delay of anywhere between 12 and 18 months)
They announced that they would be construction ready Q3 2021 - now its 1H 2022 (a delay potentially of up to a year)
They announced that completion of financing was due Q3 2021 - now its 2H 2022 (a delay of anywhere between 12 and 18 months)
They announced to have first production Q4 2023 - now its 2H 2024 (a delay of anywhere between 12 and 15 months)
WITH NO EXPLANATION!!!
I have raised my concerns before on delays being added but this is a major CF and leads me to believe there are some major problems that we don't know about and they have put this out under a "rosy project update" on nothing more than recent news that has just been out.
- Forums
- ASX - By Stock
- INR
- Ann: Rhyolite Ridge Project Update
Ann: Rhyolite Ridge Project Update, page-4
-
- There are more pages in this discussion • 11 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add INR (ASX) to my watchlist
(20min delay)
|
|||||
Last
23.0¢ |
Change
0.010(4.55%) |
Mkt cap ! $537.6M |
Open | High | Low | Value | Volume |
22.0¢ | 23.5¢ | 22.0¢ | $1.047M | 4.617M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 111194 | 23.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
23.5¢ | 926923 | 13 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 13043 | 0.230 |
1 | 70272 | 0.220 |
2 | 23513 | 0.215 |
5 | 131770 | 0.210 |
3 | 74415 | 0.205 |
Price($) | Vol. | No. |
---|---|---|
0.235 | 883123 | 10 |
0.240 | 862843 | 12 |
0.245 | 472000 | 2 |
0.250 | 1114663 | 15 |
0.255 | 40000 | 1 |
Last trade - 16.10pm 27/09/2024 (20 minute delay) ? |
Featured News
INR (ASX) Chart |