paralana 2 progress update

  1. 10,758 Posts.
    lightbulb Created with Sketch. 54
    Paralana 2 well drilling progress
    As indicated in the 12 August 2009 Weekly Drilling Report by Beach Petroleum, the Paralana 2 geothermal exploration well is at a depth of 1,427 metres and is currently drilling in the Erudina shale formation.
    The Paralana 2 well drilling campaign was originally expected to take between 2-3 months. The drilling campaign is now scheduled to take 3-4 months. The primary cause of the time extension relates to lower than expected rates of penetration (ROP) during drilling of the large diameter 17 1/2” hole in the hard rocks that are prevalent in the upper geological sequence.
    The Paralana 2 well is currently drilling the 12 ¼” section of the 4 kilometre well and the ROP has increased significantly achieving more than double previous rates."

    A sleeping bagger IMO. She should go up as this timeline progresses in expectation and once the well testing is successfully completed I expect really good gains. The timeline should be multiplied by 2 as the upvent still needs to be drilled. Total time frame 6 months until testing is underway/completed. Perhaps 10 to 12 months b4 first power generation ??
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
37.5¢
Change
0.000(0.00%)
Mkt cap ! $129.9M
Open High Low Value Volume
37.5¢ 37.5¢ 37.0¢ $17.58K 47.19K

Buyers (Bids)

No. Vol. Price($)
1 47430 37.0¢
 

Sellers (Offers)

Price($) Vol. No.
37.5¢ 35914 1
View Market Depth
Last trade - 16.10pm 25/07/2025 (20 minute delay) ?
PTR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.