I may been reading this wrongly , But the way I take it is that the RAMP UP is starting in October not the first production .
this latest announcement states
Commencement of production ramp-up remains on track for October 2021
But when you go back to the investor presentation on the 23/8
Production Imminent
2
3
4
5
Beyondie SOP Project is substantially de-risked with first production on target for
September and commercial production ramp-up to commence in October 2021
Construction near completion, commissioning commenced
100% of expanded production committed to offtake with K+S
So my way of thinking is this latest announcement is only talking about the ramp up
- Forums
- ASX - By Stock
- KLL
- Ann: Beyondie SOP Project - Operations Update
Ann: Beyondie SOP Project - Operations Update, page-37
-
-
- There are more pages in this discussion • 278 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add KLL (ASX) to my watchlist
(20min delay)
|
|||||
Last
$7.28 |
Change
0.000(0.00%) |
Mkt cap ! $2.499M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
KLL (ASX) Chart |
Day chart unavailable