2 June 2009 ASX ANNOUNCEMENT Gold plant construction and development update Gold plant refurbishment and construction 25% complete State Mining Engineer approves mining, environmental approvals awaited Development schedule on target for production to commence in December BRIGHTSTAR GOLD PROJECT Directors are pleased to report the following update on the progress of the BrightStar Gold Project development which is expected to start producing gold from December at a rate of 30,000oz per annum. SUMMARISED SCHEDULE FOR BRIGHTSTAR GOLD PROJECT JUNE 09 –JULY 09 PLANT REFURBISHMENT JULY 09 – SEPT 09 ONSITE CONSTRUCTION OCTOBER 09 PLANT AND INFRASTRUCTURE COMPLETION NOVEMBER 09 PLANT COMMISSIONING AND MINING COMMENCEMENT DECEMBER 09 COMMENCMENT OF GOLD PRODUCTION CPC Engineering report that the fixed price Plant Refurbishment, Construction and Commissioning