Dorado Timetable

  1. 923 Posts.
    lightbulb Created with Sketch. 356
    From the recent AIP Industry Briefing:
    • Commence Detailed design 2H2022
    • Commence WHP construction immediately post FID then install late 2023
    • Drilling of wells 2024/5
    Execution
    • Ready For Startup 2026
    • Liquids operations initially
    • Phase 2 gas operations anticipated post optimised oil production

    The WHP will be circa 1500T with 16 slots and will have a gravity base requiring about 30k T of ballast. The FPSO will be a converted Suez Max tanker designed for 100,000 bpd and 210 mmscfd gas compression.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
9.8¢
Change
-0.001(1.01%)
Mkt cap ! $175.3M
Open High Low Value Volume
10.0¢ 10.3¢ 9.8¢ $142.9K 1.439M

Buyers (Bids)

No. Vol. Price($)
5 678865 9.8¢
 

Sellers (Offers)

Price($) Vol. No.
10.0¢ 24854 1
View Market Depth
Last trade - 16.10pm 19/09/2025 (20 minute delay) ?
CVN (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.