Hey Willow,
I believe you are mistaken. The 16th Dec date is the date that significant works must be undertaken by. Being able to do this works was contingent on receiving 3 approvals.
1. Project Management plan. This was approved on 27/8
2. Mining Proposal. This was approved on 1/10 as you have noted
3. Mine closure plan. This was approved on 1/10 as you have noted.
Hence the early works have begun and they should easily fulfil this requirement by 16/12.
I believe I am correct is stating that the next step, Works Approval, has nothing to do with the 16/12 deadline date. It is required so they can build an industrial premises. Thats way down the line. Happy to be corrected.
- Forums
- ASX - By Stock
- VMY
- Ann: Management Change - Chief Financial Officer
Ann: Management Change - Chief Financial Officer, page-30
Featured News
Add VMY (ASX) to my watchlist
Currently unlisted public company.
The Watchlist
ACW
ACTINOGEN MEDICAL LIMITED
Will Souter, CFO
Will Souter
CFO
Previous Video
Next Video
SPONSORED BY The Market Online