Stingemore,
you are right, generallay when they start there precommissioning they put water then ore through to check flow and make sure there are no bottlenecks, leaks nuisence trips and the like.
Once they are confident that there are no issues as indicated above then then the commissioning can start.
They will start to introduce low grade ore and start to introduce the chemials and start ramping up throughput and progessively increasing the grade and quantity of the ore.
This can ramp up fairly quickly but they usually announce it is fully commissioned once they have proven all systems through to a gold pouring stage with a noninated period or amount of gold or throughput can operate consistenly non stop.
Como engineering have lots of experience in gold so I really think they will get through this fairley quickly.
If the engineering and installation are done well, a mine can be in full production within weeks but the call as commissioned may come some time later dependent on the contract conditions as to what is classified as commissioned and FML take over fully running the plant.
A simplistic explanation but I think covers off the most of what the commissioning involves.
- Forums
- ASX - By Stock
- FML
- how good is this
how good is this, page-8
-
- There are more pages in this discussion • 2 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add FML (ASX) to my watchlist
(20min delay)
|
|||||
Last
17.5¢ |
Change
0.005(2.94%) |
Mkt cap ! $50.14M |
Open | High | Low | Value | Volume |
16.5¢ | 17.5¢ | 16.5¢ | $22.19K | 132.8K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 28446 | 17.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
17.5¢ | 35235 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 28446 | 0.170 |
2 | 56458 | 0.165 |
3 | 101933 | 0.150 |
2 | 9041 | 0.145 |
2 | 23627 | 0.140 |
Price($) | Vol. | No. |
---|---|---|
0.175 | 35235 | 1 |
0.180 | 2846 | 1 |
0.190 | 1460 | 1 |
0.195 | 102564 | 1 |
0.200 | 5000 | 1 |
Last trade - 14.56pm 18/10/2024 (20 minute delay) ? |
Featured News
FML (ASX) Chart |