TBA 0.00% 2.6¢ tombola gold ltd

Risks for Tombola, page-18

  1. 191 Posts.
    lightbulb Created with Sketch. 67
    You're dead right, mea culpa. I've seen Golden Mile and Mt Freda mentioned together so often that I must be associating them together. This still beggars the question "where is the crusher?". As Freddieflintoff mentioned it is in the processing plant diagram, but to me that is just a piece of paper at this stage. If I wrote $1,000,000 on a post-it note, that doesn't make me a millionaire. From what I can tell, the following major components still need to be installed:
    • Power
    • Crusher
    • Feeder
    • Pumps
    • Elution Boiler
    • Eluate Tank
    • Smelter
    The best picture I can see of the site is this from the quarterly on p4, showing the site office, ponds, a hopper, and the four vats. That doesn't seem to be enough progress to get this to gold pour capability by early Q3:
    https://hotcopper.com.au/data/attachments/4359/4359969-60c583749f9f001506f57dfd9b77b8df.jpg
 
watchlist Created with Sketch. Add TBA (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.