• On-track for planned August plant shutdown and re-start in September, with targeted ramp-up to nameplate capacity testing in Q4 CY2022.
• Targeting 80 ktpa SOP production run-rate by Q1 CY2023, followed by further ramp-up to 120 ktpa production target run-rate by Q3 CY2024.
- Wow so we will see the 120ktpa end of 2024??? WTF is going on?
- “During the past quarter we have substantially de-risked Beyondie. We have validated the overall process design, strengthened our technical teams and skills base, and have achieved our first sales into a buoyant pricing environment.
The progress made in de-risking is playing an important part in our process to secure the additional funding which we identified as required to mitigate the challenges of being the first producer in a new industry. We expect to announce the details of our targeted funding solution in the coming weeks.
- How much and when does the additional funding end??? I have no words![]()