Galena Mining Limited (G1A) - Abra reaches 83% completion (Petra 19/9/22)
G1A released its monthly update for its 60% owned Abra lead-silver project in WA, with construction now 83% complete. G1A expects total project expenditure to be A$231m, with A$40m in spend remaining (Figure 2). Importantly, the delivery of the floatation cells and regrind mill to Australia means all key pieces for the processing facility have arrived.
First production remains on track for Mar. Q’23.
We maintain our BUY recommendation and A$0.44/sh price target.
- Forums
- ASX - By Stock
- G1A
- Ann: Abra Construction 83% Complete
Ann: Abra Construction 83% Complete, page-20
-
- There are more pages in this discussion • 10 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add G1A (ASX) to my watchlist
|
|||||
Last
5.9¢ |
Change
0.000(0.00%) |
Mkt cap ! $44.40M |
Open | High | Low | Value | Volume |
0.0¢ | 0.0¢ | 0.0¢ | $0 | 0 |
Featured News
G1A (ASX) Chart |
Day chart unavailable