"50% of production or 113,000 tonnes, whichever is greater."
How do they establish the tonnage ? I mean, let's say they mine 220k tonnes as per the announcement (yes I know officially it said 163k tonnes, but they did say they expect 220k). Do PLL get the first 113k tonnes, or do they just ensure they eventually get the 113k tonnes for that year ? Let's say they only forecast 120k tonnes for next year after starting up the plant - I can't see any contract being so far in favor of one party, that PLL get the entire 113k tonnes before SYA get any.
If only we had the full contract to peruse, not just a few paragraphs in a PFS.
- Forums
- ASX - By Stock
- SYA
- General Discussion Topics
General Discussion Topics, page-74684
-
- There are more pages in this discussion • 69,980 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add SYA (ASX) to my watchlist
(20min delay)
|
|||||
Last
3.6¢ |
Change
0.003(9.09%) |
Mkt cap ! $370.5M |
Open | High | Low | Value | Volume |
3.3¢ | 3.7¢ | 3.2¢ | $2.985M | 85.61M |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
10 | 4176281 | 3.5¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.6¢ | 546675 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
9 | 4126281 | 0.035 |
13 | 4271453 | 0.034 |
32 | 12081348 | 0.033 |
71 | 14499876 | 0.032 |
36 | 9777461 | 0.031 |
Price($) | Vol. | No. |
---|---|---|
0.036 | 546675 | 2 |
0.037 | 10478059 | 38 |
0.038 | 16389346 | 31 |
0.039 | 5671797 | 19 |
0.040 | 6594768 | 34 |
Last trade - 16.10pm 16/10/2024 (20 minute delay) ? |
Featured News
SYA (ASX) Chart |
The Watchlist
JBY
JAMES BAY MINERALS LIMITED
Andrew Dornan, Executive Director
Andrew Dornan
Executive Director
SPONSORED BY The Market Online