    26 February 2010
    Weekly Drilling Update on J-50 Exploration Well (SV Akkar)
    The Board of Jupiter Energy Limited (ASX: JPR) is pleased to provide its weekly
    update report on the drilling of the J-50 Exploration Well (referred to in previous
    announcements as SV Akkar).
    J-50 reaches 2470mRT in 216mm hole before drilling ahead to core
    the primary Middle Triassic target.
    1. Well Name / Permit: J-50, Block 31, Mangistau, Kazakhstan
    2. Reporting Period: The period to 1200hrs 25 February 2010
    (GMT +5)
    3. ASX Release Time and Date: 0700 hrs 26 February 2010
    4. Report No: 8
    5. Spud Date: 2330hrs, 29 December 2009 (GMT +5)
    6. Rig: Astra Star Rig #1 (Turnkey Contract)
    7. Days Since Spud: 57.52
    8. Location of Well: Latitude: 4346'43.8" N
    Longitude: 5150'0.78" E WGS 84
    9. Elevation: G.L. 145m MSL
    R.T. 150.5m MSL
    10. Proposed Depth: 3200 - 3300 metres
    11. Target(s): Primary Objective: Middle Triassic at
    approximately 2920mRT.
    Secondary Objective: Nil
    12. Present Depth: At 1200hrs 25 February 2010 (GMT +5)
    depth was 2470mRT.
    13. Current Geological Section
    and Hydrocarbon Shows:
    Formation: Jurassic sandstones, siltstones
    and limestone with some coal.
    Hydrocarbon Shows: 2265-2285m, weak
    streaming yellow-white cut fluorescence;
    2310-2320mRT, weak streaming blue-white
    cut fluorescence.
    14. Operations since last Report: Drilled ahead in 216mm hole to 2298mRT.
    Conducted survey. Pulled out of hole and
    changed out drilling jars and inspected bit.
    Conducted rig service. Ran in hole. Drilled
    ahead in 216mm hole to 2461mRT.
    Conducted wiper trip and survey. Pulled
    out of hole to 1180mRT and conducted rig
    maintenance. Ran in hole and drilled
    ahead in 216mm hole.
    15. Current Operations: At 1200 hrs 25 February 2010 (GMT +5),
    current activity was drilling ahead in
    216mm hole at 2470mRT.
    16. Future Operations: Continue drilling 216mm hole to
    2700mRT. Conduct wiper trip and survey.
    Continue drilling ahead to core point.
    17. Well/Prospect Description: The J-50 well tests the primary Middle
    Triassic objective in a structural horst trap
    immediately on trend with the oil
    producing North Akkar Field. This location
    tests a play with an estimated 20 mmbbl
    recoverable mapped within Block 31.
    18. Participants in well: Jupiter Energy Limited 100%
    Update and planning meetings with the Contractor have continued on an almost
    daily basis.
    The efficiency of drilling operations improved this week. Overall meterage was
    less than planned however, the amount of time spent drilling ahead increased.
    Work has continued with the contractor to improve operational efficiency and this
    is reflected in the improved surveying and tripping times.
    Temperatures in the region have risen this week with maximum temperatures in
    Aktau reaching highs above 0⁰C for several days. High winds have impacted rig
    operations and made it very difficult to handle drill pipe in the derrick on several
    occasions.
    For further information please contact:
    David Thorpe , Managing Director, Jupiter Energy Limited on +61 (0)8 9322 8222
    ENDS
 
watchlist Created with Sketch. Add JPR (ASX) to my watchlist
(20min delay)
Last
2.8¢
Change
-0.002(6.67%)
Mkt cap ! $35.68M
Open High Low Value Volume
2.8¢ 2.8¢ 2.8¢ $6.02K 215K

Buyers (Bids)

No. Vol. Price($)
1 141968 2.2¢
 

Sellers (Offers)

Price($) Vol. No.
3.0¢ 503699 1
View Market Depth
Last trade - 14.55pm 08/11/2024 (20 minute delay) ?
JPR (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.