    That is not how capacity factor works. For solar you need to remenber that half the time the sun isn't shining, so already you are at 50%. The capacity factor is the average power produced divided by the rated power, or the actual power produced over a period of time (kWh) divided by the theoretical power. Some solar farms are up to 25%, but 20% is a reasonable average.

    The 30% quoted is pure speculation based on virtually nothing other than than some computer modelling, maintenance assumptions, tank testing and enthusiasm.

    If the CETO 5 units were rated at 240kW each and worked perfectly all year at their rated capacity they would have produced (3x240x24x365) - 6,307,200 kWh. CETO 5 only produced 12,000kWh over the test period (https://www.carnegiece.com/portfolio/ceto-5-perth-wa/). That is a capacity factor of less than 0.2%.


 
watchlist Created with Sketch. Add CCE (ASX) to my watchlist
(20min delay)
Last
4.2¢
Change
-0.001(2.33%)
Mkt cap ! $15.38M
Open High Low Value Volume
4.2¢ 4.3¢ 4.2¢ $5.242K 124.5K

Buyers (Bids)

No. Vol. Price($)
1 28049 4.2¢
 

Sellers (Offers)

Price($) Vol. No.
4.3¢ 494790 9
View Market Depth
Last trade - 15.47pm 28/06/2024 (20 minute delay) ?
CCE (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.