ESS 0.00% 50.0¢ essential metals limited

General Discussion, page-1432

  1. w27
    2,471 Posts.
    lightbulb Created with Sketch. 768
    Production of 180,000 tons of concentrate from 1.6m tons of ore is just above 50% recovery. No metallurgist worth his salt would accept that recovery. I think you are taking figures from a proposal to use dense media separation as a first stage. This could be used for a start-up while the plant was built, but tails would be kept for further processing when the flotation unit was completed. This would probably require a finer grind and therefore more grinding mills to complete the recovery. That is a not uncommon start-up installation, but the first tails would be processed through the flotation section when it was built to ensure best recovery of the valuable metal.
 
watchlist Created with Sketch. Add ESS (ASX) to my watchlist

Currently unlisted public company.

arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.