    Someone should have proofread this and added an explanation as to the fact we have passed "early March" without any announcement Bit sloppy.

    Workflow during the December quarter was further disrupted by weather events during November
    and December. However, by the end of the December quarter :
    • flowlines and export pipelines were completed and had been successfully pressure tested.
    • mechanical installation was underway with lease foundations in place at Vali-1 and Vali-3.
    Skids and pipework were on site and largely assembled.
    • metering facility foundations were near completion, risers in place and metering equipment
    moved into place for installation on return from the Christmas New Year break.
    Work resumed in January 2023, albeit affected by further rainfall and extreme heat restrictions.
    Mechanical handover of the facilities at Vali-1 took place on Saturday 11 February and well
    commissioning is underway with first gas anticipated in the 2nd half of February. Construction and
    installation work is ongoing at the Vali-2 and Vali-3 sites. Mechanical handover and commissioning
    at these locations is anticipated to occur by early March.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
0.3¢
Change
0.000(0.00%)
Mkt cap ! $5.511M
Open High Low Value Volume
0.0¢ 0.0¢ 0.0¢ $0 0

Buyers (Bids)

No. Vol. Price($)
11 6950909 0.2¢
 

Sellers (Offers)

Price($) Vol. No.
0.3¢ 10732453 8
View Market Depth
Last trade - 16.21pm 07/08/2025 (20 minute delay) ?
MEL (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.