April 27 (Reuters) - Adbri Ltd (ABC) :
- ADBRI LTD - KWINANA UPGRADE PROJECT UPDATE
- ADBRI LTD - REMAINING CAPITAL COMMITMENT FOR PROJECT COMPLETION IS NOW ESTIMATED TO BE BETWEEN APPROXIMATELY A$185 MILLION - A$220 MILLION FOR KWINANA
- ADBRI LTD - AS AT END OF MARCH 2023, ADBRI HAD COMMITTED A$199 MILLION FOR KWINANA PROJECT, WITH A$143 MILLION SPENT
- ADBRI LTD SEES TOTAL PROJECT COST ESTIMATE FOR KWINANA UPGRADE TO BETWEEN A$385 MILLION - A$420 MILLION
- ADBRI - STRUCTURAL & PIPING QUANTITIES AT KWINANA GREATER THAN ANTICIPATED, FURTHER IMPACTING ON PROCUREMENT AND CONSTRUCTION COSTS AND HOURS
- ADBRI - REVIEW CONFIRMED PROJECT REMAINS ON TRACK FOR TARGET COMMISSIONING IN Q2 2024, WITH NEW PLANT EXPECTED TO BE FULLY OPERATIONAL IN Q3 2024