It seems the changes in financials were all focused on getting CAPEX down and pay-back period down (and IRR up).
Those are not quite the same as maximizing NPV, but are still beneficial to shareholders - more chance of successful funding.
-$23m. Smaller mining fleet.
-$52m. No ore sorters upon start-up. But 0.9 year payback, then use those funds to add ore sorters after 1 year. +$44m and +$30m.
-$36m. Remove a generator. But relies on mains power actually happening.
+$26m for a haul road from RPM to Korbel. Necessary.
- Forums
- ASX - By Stock
- NVA
- Ann: Robust Phase 2 Scoping Study for the Estelle Gold Project
Ann: Robust Phase 2 Scoping Study for the Estelle Gold Project, page-59
-
-
- There are more pages in this discussion • 87 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add NVA (ASX) to my watchlist
(20min delay)
|
|||||
Last
28.0¢ |
Change
0.030(12.0%) |
Mkt cap ! $76.14M |
Open | High | Low | Value | Volume |
25.0¢ | 28.0¢ | 25.0¢ | $64.69K | 238.6K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
3 | 168269 | 25.0¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
28.0¢ | 16999 | 2 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
3 | 168269 | 0.250 |
3 | 44000 | 0.240 |
1 | 25000 | 0.235 |
7 | 341586 | 0.230 |
7 | 115615 | 0.225 |
Price($) | Vol. | No. |
---|---|---|
0.280 | 3999 | 1 |
0.285 | 36000 | 2 |
0.290 | 25000 | 1 |
0.300 | 26908 | 3 |
0.305 | 79219 | 2 |
Last trade - 16.10pm 01/11/2024 (20 minute delay) ? |
Featured News
NVA (ASX) Chart |