    Pr +Nd oxide cost ~48k/ton. That's just Pr+Nd not including all the other REE's
    Grade of East Laverton deposit, low ball at 1,000ppm TREO, thickness ~10metres, density say 1.8, percent of Pr+Nd 19.5% Size of deposit 12km2.
    So for every 1km2 the tons would be 1000m(length) X 1000m (Width)x 10m (thickness)x 1.8 (density) = 18Mt.
    18Mt x 1000ppm (0.1%)TREO x 19.5% Pr+Nd = 35,100 ton contained Pr+Nd per km2.
    35,000 x $48,000/ton = USD1,684,800,000. 1.6 billion/km2, contained value of Pr+Nd.
 
Add to My Watchlist
What is My Watchlist?
A personalised tool to help users track selected stocks. Delivering real-time notifications on price updates, announcements, and performance stats on each to help make informed investment decisions.
(20min delay)
Last
76.5¢
Change
0.005(0.66%)
Mkt cap ! $399.1M
Open High Low Value Volume
77.0¢ 82.0¢ 74.0¢ $5.004M 6.495M

Buyers (Bids)

No. Vol. Price($)
2 16315 76.0¢
 

Sellers (Offers)

Price($) Vol. No.
76.5¢ 22847 1
View Market Depth
Last trade - 16.10pm 25/07/2025 (20 minute delay) ?
MTM (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.