Hi @CguvSorry I missed your question. I still think there is a liklihood of 1000tpa plant commissioning being complete by mid October.
In relation to PEAK Microcap Conference Presentation, It was recently said "nothing in this presentation is new. It’s still all fluff."Within the presentation there is one project update that may have been missed by a few and perhaps worth highlighting."Majority of equipment was on site by 30 June 2023 with dry commission completed.Full commissioning and start of operations targeted for 30 September 2023."
Remembering that the plant commissioning is a 5 Stage process and that dry commission is Stage 2, we are now working towards Stage 3. (Wet Commissioning).
Stage 4 Load Commissioning and then Stage 5 Full Commissioning are still targeted for 30 September 2023.
After removing gremlins, the first Mg ingots by mid to late November is still a possibility. Imo
Regards
- Forums
- ASX - By Stock
- LMG
- Ann: LMG PEAK Microcap conference presentation 13-Jul-23
Ann: LMG PEAK Microcap conference presentation 13-Jul-23, page-37
-
- There are more pages in this discussion • 12 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add LMG (ASX) to my watchlist
(20min delay)
|
|||||
Last
3.7¢ |
Change
0.000(0.00%) |
Mkt cap ! $86.87M |
Open | High | Low | Value | Volume |
3.8¢ | 3.9¢ | 3.6¢ | $35.92K | 951.1K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
1 | 24999 | 3.7¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
3.8¢ | 134036 | 1 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
1 | 24999 | 0.037 |
4 | 89923 | 0.036 |
11 | 1535539 | 0.035 |
2 | 236325 | 0.034 |
1 | 29600 | 0.033 |
Price($) | Vol. | No. |
---|---|---|
0.038 | 134036 | 1 |
0.043 | 536500 | 3 |
0.044 | 4100 | 2 |
0.045 | 45511 | 2 |
0.046 | 350000 | 3 |
Last trade - 16.10pm 09/08/2024 (20 minute delay) ? |
Featured News
LMG (ASX) Chart |