350 tpd isn't even close.
Sugar Zone's mill is 650 tpd, and is easily expanded to 1000 tpd.
Here's the outline of Harte's plan to expand it to 1400 tpd (year 2020 costs, in C$)
EXPANSION TO 1,400 TPD
Estimate of $23 million to be spent in 2020 on expanding throughput capacity:
► Additional cone crusher
► Second ball mill in parallel
► Storage modifications and additional conveyors for the ball mill
► Three additional flotation cells
► Concentrate regrind and leaching equipment
- Forums
- ASX - By Stock
- SLR
- Ann: Quarterly Activities Report
Ann: Quarterly Activities Report, page-136
-
-
- There are more pages in this discussion • 126 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
NEWS
Antler Copper Project hits major permitting milestone – air quality permit advances to final review
LU7
Discover the strong preliminary feasibility of the Bécancour Lithium Refinery, showcasing resilience in a low pricing environment and a strategic plan to capitalize on future price recoveries