STX 0.00% 20.0¢ strike energy limited

South Erregulla #3, page-132

  1. 618
    3,200 Posts.
    lightbulb Created with Sketch. 2122
    Some key takeaway points:

    Walyering gas has been even better than expected in terms of energy content, so we are getting better pricing than spot.

    SE Phase 1 will only come online early/mid 2025 as had been suspected here. By the time we enter FID by end of this calendar year say, it will be 12-16 months from start to being trucked and assembled on site.

    With industrial gas consumption taking up 90% of the current gas production in WA, new industrial projects to come online will incrementally add to the total consumption. I believe the next one off the rank is WES's Mt Holland Lithium project. It wouldn't surprise me one bit if they are our customer for half of the SE Phase 1 gas.

    As WA approaches full decommissioning of its coal-powered plants, it will add 20% to the daily total gas demand. In essense, with no other large supply to come online within the next 2-3 years, STX will be the key clog in that supply/demand tug of war.

    618

 
watchlist Created with Sketch. Add STX (ASX) to my watchlist
(20min delay)
Last
20.0¢
Change
0.000(0.00%)
Mkt cap ! $579.3M
Open High Low Value Volume
20.0¢ 20.3¢ 19.5¢ $461.2K 2.311M

Buyers (Bids)

No. Vol. Price($)
75 1744884 19.5¢
 

Sellers (Offers)

Price($) Vol. No.
20.0¢ 1876659 53
View Market Depth
Last trade - 13.09pm 29/07/2024 (20 minute delay) ?
STX (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.