Ann: Tindalo Operations Update , page-5

  1. 1,012 Posts.
    Ya,

    I'll stick by my Wed next week timing to have the well back flowing but looking at where they are now it may actually be a few days earler.

    They will be sidetracking out of 7" liner (6" hole) and 5" or 4-1/2" pre-drilled or slotted (even NDO don't seem to know which) liner.

    There are train-wreck scenarios which could happen with the physical well construction - could turn a whipstock, not be able to get back through the window, stick a liner hanger running tool and probably a few more... but those are small small likelyhood and how unlucky do you feel?

    As for conductive faults - I think that they would have considered it and had a look at any faults which crossed the original wellbore on the image log - they would have been pouring over that looking for the water source... giving up on fishing (retrieve) guns and logging means that they are 99% sure that the liner is uncemented - otherwise they would take the time to fish and log.

    In any case - if they have put as much cement out through those perfs as I would (and I bet they have) then any conductive fault or fracture is pretty much full of cement.

    I'm still confident that we will have an excellent result here!
    p1000
 
watchlist Created with Sketch. Add RPM (ASX) to my watchlist
(20min delay)
Last
6.9¢
Change
0.000(0.00%)
Mkt cap ! $17.40M
Open High Low Value Volume
6.9¢ 6.9¢ 6.9¢ $21.83K 316.4K

Buyers (Bids)

No. Vol. Price($)
1 39215 6.9¢
 

Sellers (Offers)

Price($) Vol. No.
7.0¢ 239702 3
View Market Depth
Last trade - 15.58pm 10/07/2024 (20 minute delay) ?
RPM (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.