    Your response is aligned. Construction is typically a 3 year process all going well. As per any major infrastructure project the runway before and after is as long if not longer hence the ~10 year timeframe. Construction can often be the quickest part. The front end feasibility, approvals, financing and tenders can be quite difficult and elongated.

    • Feasibility Study/Design
    • Approvals - Land, Easements, Water
    • Market Engagement - Commercial model, financing, Tender
    • Tender Award
    • Mobilisation - recruitment, sub contracts etc
    • Procurement
    • Construction - 3 years
    • Commissioning
    • Handover
    • Operations
 
watchlist Created with Sketch. Add HCH (ASX) to my watchlist
(20min delay)
Last
90.0¢
Change
-0.030(3.23%)
Mkt cap ! $136.2M
Open High Low Value Volume
92.0¢ 93.0¢ 90.0¢ $70.14K 76.45K

Buyers (Bids)

No. Vol. Price($)
2 2799 90.0¢
 

Sellers (Offers)

Price($) Vol. No.
91.0¢ 6237 1
View Market Depth
Last trade - 16.10pm 26/07/2024 (20 minute delay) ?
HCH (ASX) Chart
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.