HGO 2.78% 7.4¢ hillgrove resources limited

Broker Coverage, page-46

  1. 359 Posts.
    lightbulb Created with Sketch. 15
    I don't believe they're in production yet. From the announcement on the 10 January were the following two comments:
    "The wet plant will commence commissioning next week." So commissioning may have started as late as 17 January, maybe later if there were delays.
    "Over the next couple of weeks, we will commission the wet circuit of the processing plant with first copper production shortly
    thereafter." Commissioning may take 3-4 weeks but could be longer.

    I'd love to see an announcement confirming that commissioning is complete and production is underway but get the feeling we may need to be patient for a bit longer.
 