Hi Stirer,
can you please run the numbers so all can see.
the plant WKT purchased has a capacity (throughput) of 300k tonnnes.
mike states the TGC grade is ~15%
when Mike states he expects it to take 9 months to hit the recovery of 86% (40k tpa)
how can WKT achieve this after 4 months with only achieving 50% recovery?
300kx 50% recovery = 150t x 15% TGC = 22.5k tpa
300k x 100% recovery =300k x 15% TGC = 45k tpa.
can you see your error, you have assumed the plant is larger than what Mike has stated, or you assume the recovery is going to be 100% from day one or WKT will be processing a much higher TGC grade than the mine plan in the IRR report.
if anyone listens to your numbers, they are going to get burnt badly
- Forums
- ASX - By Stock
- WKT
- Ann: Expiry of BMCG funding facility
Ann: Expiry of BMCG funding facility, page-319
-
- There are more pages in this discussion • 100 more messages in this thread...
You’re viewing a single post only. To view the entire thread just sign in or Join Now (FREE)
Featured News
Add WKT (ASX) to my watchlist
(20min delay)
|
|||||
Last
10.0¢ |
Change
0.000(0.00%) |
Mkt cap ! $67.12M |
Open | High | Low | Value | Volume |
10.0¢ | 10.0¢ | 10.0¢ | $39.61K | 396.1K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
2 | 125500 | 9.9¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
10.5¢ | 220113 | 3 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
2 | 125500 | 0.099 |
2 | 370416 | 0.096 |
2 | 92238 | 0.095 |
1 | 83946 | 0.092 |
3 | 325000 | 0.090 |
Price($) | Vol. | No. |
---|---|---|
0.105 | 220113 | 3 |
0.110 | 13720 | 2 |
0.115 | 120000 | 2 |
0.120 | 419902 | 8 |
0.125 | 515166 | 8 |
Last trade - 15.54pm 19/08/2024 (20 minute delay) ? |
Featured News
WKT (ASX) Chart |