    Upcoming Drilling
    The planned re-commencement date for KRR’s 2024 RC drill programme has been postponed due to heavy rains after Cyclone Lincoln. Drilling is scheduled to commence once access conditions improve, expected mid-March.
    The first phase of drilling, this year, will prioritize Tennant Creek East, focusing on three main areas. The first area to be tested will be the Commitment area (4 RC holes planned for 800m), followed by the Langrenus area (10 holes for 1,500m), then the Providence area to follow up on the newly discovered geochemically anomalous ironstones, alteration and structures associated with gravity and dipole-dipole induced polarization (DDIP) anomalies.
 