how much progress???
Dr Pepper quoted on Monday that steelwork 90% done, now admittedly, the webcam not real clear, but I can't see any steel supports which have been installed on the upper 4 levels of the total 10 levels where the sign is being installed. If I am correct, then there is no way that 90% of the installation has occured. Judging by previous photos, seems like they are installing about 1-2 levels of vertical steel work per week, and as they had only completed 2 levels as of the most recent photos 2 weeks ago, I'm guessing that around 6 levels max have been installed which would make no more than 60% complete. What happened to the promised weekly photo update on the Lumacom website?