This pregnant pig is way overdue for releasing information to the market and shareholders.
According to the PSA Investor Presentation on 25 November - over a month ago, the following were supposed to happen:
1. Main Pass 19:
Drill December 2004 - 3 wells
2. Beibu:
Pre-feasibility study due December 2004
3. Vermilion 258
50% production increase December 2004
Well its December 30 and not one bit of information about any of the above let alone the LA wells started on 4 November - 7 weeks and counting and not one word about those either!!!
I guess it is time for a letter to the USA SEC about the above matters.