    Construction commences for sustainable lithium project with Pilbara Minerals
    • 5 July 2024




    The Mid-Stream Demonstration Plant Project, that aims to produce a low-carbon energy intensity lithium salt in a joint venture with Pilbara Minerals, moved into construction phase in the June Quarter 2024.
    Bulk earthworks at Pilbara Minerals’ Pilgangoora Operation are complete. The site is ready for concrete and detailed earthworks, with preferred contractors selected.

    Off-site fabrication of key equipment is well progressed, including the Calix electric calciner, structural steel modules and tanks, with many equipment packages being dispatched to the site.

    The project remains on time and budget, with commissioning due to commence in the March Quarter 2025 and the first lithium salt production targeted for the June Quarter 2025.



    To learn more about Calix’s technology and the opportunity for sustainable processing of critical minerals, read our white paper here: https://calix.global/news/sustainable-critical-minerals-and-the-green-export-opportunity/
    Back to news

    https://calix.global/news/construction-commences-sustainable-lithium-project-pilbara-minerals/
 
watchlist Created with Sketch. Add CXL (ASX) to my watchlist
arrow-down-2 Created with Sketch. arrow-down-2 Created with Sketch.